Sunshine Coast University Hospital PPP.

To meet the needs of the rapidly growing Sunshine Coast region, the Queensland Government allocated $1.8 billion to construct and establish a new tertiary teaching hospital at Kawana.

The hospital opened in early 2017 with approximately 450 inpatient beds, expanding to 738 by 021/22.

Roger from P2P undertook the role of Technical Director and led the technical team supporting the masterplan, preliminary assessment, business case and transactions for both the 200 bed co-located private hospital and the Public Private Partnership (PPP) contract for the 738-bed public tertiary teaching hospital.

Embedded within the project team for over three years, Roger guided the development of the technical output specifications for the public and private hospitals, including all interactive design and technical evaluation stages.

 